Interfaith Community Shelter Ready to ROCk, but is Santa Fe?

A full house at the Genoveva Chavez Community Center on April 9 heard from ICS about theROCk. Mayor Michael Garcia and Councilor Paul Bustamante both attended in support, though the event was not sanctioned by the city.

Board Chair Kent Grubbs walked through where the project came from and where it stands. Work began nearly four years ago. The Emblem Road property was acquired in January. Construction is projected at about $16 million, and running the facility would cost $2.5 to $3 million a year. Grubbs also said ICS will not break ground until 80 percent of the money is raised, and that with no state capital outlay this year the path runs through fundraising.

The forum was run as facilitated roundtables rather than an open microphone, and the comments collected there were documented for follow-up. This is a full-length feature, and it does not leave out the harder moments in the room.

Santa Fe Reporter, April 14, 2026. By Dave Cathey.

Read the full story at sfreporter.com